Changeovers reports
The Changeovers tab shows the production periods by types and the corresponding calculated Changeover Gap for the line over a specific time period.

Legend
Click on the elements in the legend to show or hide them. Hidden elements are grayed out in the legend, and the preceding icon is rotated.
Element | Description |
---|---|
Production Duration |
Duration of production of a type |
Changeover Gap |
Duration of the changeover gap for a type |
Changeover gap
The Changeover Gap for a production line is the calculated time that a changeover of the whole line would theoretically have taken. It is based on a complex algorithm and takes into account, among other things, the changeover times of each facility of the line, but cannot always be calculated. The changeover time of the last facility is used as a fallback.